On a warehouse or an apartment build, a construction loan monitor can stand on the slab and see what the draw is paying for. On a food processing plant, a substation upgrade or a data center, a large share of the money leaves before anything arrives. Equipment is ordered, a milestone is invoiced, and the funds move against a line on a schedule of values describing something sitting in a manufacturer's shop four states away.
That is not an unusual structure. It is how capital equipment has always been bought. The problem is that the controls built for vertical construction do not transfer to it, and most files carry one protection where they need four.
Why the usual check does not apply
Percentage-complete verification works because the work is physically present and observable. A field inspector confirms that the steel is up and the draw matches. Stored materials break that logic in two places at once: the asset is not on site, and the thing being certified is a contractual milestone rather than a physical condition.
A purchase order milestone such as "engineering release" or "materials procured" is a commercial event. It is met or not met according to the contract's own definition, which is often loose. An invoice referencing it looks exactly like an invoice referencing completed work. It reconciles cleanly to the schedule of values. And it can be entirely unsupported.
The four protections
Where a lender funds equipment that is not on site, the file should show all four of the following. In practice most files show one, usually the insurance certificate, because it is the one somebody asks for at closing.
- A bailee letter. The party holding the equipment — the manufacturer, a fabricator, a warehouse — acknowledges in writing that it is holding specific, identified goods for the lender's benefit and will not release them except on the lender's instruction.
- A UCC-1 filing. Filed against the borrower, describing the equipment specifically enough to be identifiable, in the correct jurisdiction. A blanket filing on "all equipment" is weaker than it looks when a manufacturer's own secured creditor appears.
- Insurance naming the lender as loss payee. Covering the equipment where it actually sits, which is frequently not where the policy says it is. Builder's risk written for the project site does not necessarily cover a transformer in a yard in another state.
- Physical segregation and tagging. The equipment identified as belonging to this project, stored separately, with serial numbers recorded. Without this, nothing above is enforceable against a bankruptcy trustee, because nobody can say which units are the ones the lender paid for.
Any one of these on its own is an unsecured advance with paperwork attached. The protection comes from the set.
Front-loaded milestones
A second exposure sits inside the payment schedule. Equipment purchase orders routinely carry terms like thirty percent at order and twenty-five percent at engineering release. That means fifty-five percent of a multi-million dollar package can be funded before fabrication begins in earnest.
That structure is not fraud and it is not unusual. It is a supplier financing its own working capital, which is a reasonable thing for a supplier to want. The question is whether the lender knows it is the party providing that financing, and whether the loan is sized and secured on that basis. On most files the answer is that nobody computed it.
The test is simple and almost never run: at any point in the draw schedule, what percentage of the equipment package has been funded, and what percentage has been physically produced? When the first number leads the second by a wide margin, the loan is carrying supplier performance risk that was never priced.
Acceptance testing as a payment condition
Major equipment is typically subject to a factory acceptance test before shipment and a site acceptance test after installation. In a well-written purchase order, passing the factory test is a condition of the milestone payment that follows it.
In practice the payment usually releases on an invoice date. The test gets scheduled, or partially completed, or witnessed by someone who signs a form nobody reads. By the time a problem appears, the unit is installed, the retainage is gone, and the contractual leverage that existed before shipment is no longer available.
Three questions answer most of this: was the test performed, who witnessed it, and did the results match the specification the purchase order referenced? If a draw package funds an acceptance milestone and contains no test report, that is a finding regardless of how complete the rest of the file looks.
Lead time as a budget item
Long-lead equipment — transformers, switchgear, large generators, specialized process equipment — has carried quoted lead times well beyond historical norms for several years. Quoted is the operative word. A quoted lead time is a commercial representation, not a commitment, and it is frequently optimistic relative to the manufacturer's actual backlog.
When the real lead time exceeds the construction schedule, the consequence is not just a late project. It is an interest reserve calculated against a completion date that will not happen. That shortfall surfaces late, when the reserve is nearly exhausted, and it arrives as a request for an extension on a loan that is no longer performing to its original terms.
What this means for a file
None of this requires a site visit. It requires reading the purchase orders, the payment schedule, the acceptance test documentation and the collateral filings, and asking whether the money that has gone out is supported by anything the lender could enforce.
That is a document review, and it is a different discipline from field observation. A monitor who is good at verifying work in place is not necessarily equipped to tell a credit officer whether a $6 million equipment package is priced at market or whether a milestone structure leaves the lender exposed. Those are commercial questions, and they are answered before the concrete is poured.
Steven L. Haskins is the principal of Haskins Capital LLC. He spent twenty-plus years on the owner's side of capital projects, including procurement lead on a $1 billion greenfield program, and currently serves as Director of Capital Expenditures at a transformer manufacturer. Haskins Capital provides commercial and contractual review for project owners and, separately, for the institutions that finance capital projects.
This article is general commentary and does not constitute legal, engineering or financial advice.